Nine Thousand Square Meters! Huqiu Plant of China State Construct Commercial Concrete Poured a “Good Start”
By:CWCG    Date:2024/02/13    Font size:A+A-Printing

At 17:00 on January 17, 2024, Southern Jiangsu business division Huqiu Plant of China State Construct Commercial Concrete Co., Ltd. successfully completed the pouring of nearly 9,000 square meters of floor for the main 1# building of Suzhou Integrated Circuit Innovation Center (Phase II) Project, breaking the record of China State Construct Commercial Concrete ’s single-day concrete production on January 16, welcoming a “good start” for year of 2024.








At 17:00 on January 17, 2024, Southern Jiangsu business division Huqiu Plant of China State Construct Commercial Concrete Co., Ltd. successfully completed the pouring of nearly 9,000 square meters of floor for the main 1# building of Suzhou Integrated Circuit Innovation Center (Phase II) Project, breaking the record of China State Construct Commercial Concrete ’s single-day concrete production on January 16, welcoming a “good start” for year of  2024.









Facing the reality of high demand for materials and gate closure of shipping routes, the material personnel of Huqiu Plant actively negotiated with the suppliers, adjusting the transportation routes in time, and closely cooperating with many parties to ensure the normal supply of sandstone aggregate through the combination of shipping and land transportation.


In order to avoid the influence of sandstone raw material batches, the technicians organized and carried out a number of mix proportion verification tests to distinguish between different batches of sandstone and to ensure stable quality of concrete.










The personnel of all departments cooperated with each other, finally, in 35 hours, with 6 pumps and more than 600 mixer trucks, Huqiu Plant successfully completed this large volume of floor pouring task, which gained the unanimous praise from the project side.






It is reported that the project is a major project in Jiangsu Province, with a total construction area of 211,700 square meters. The 1# main building is an ultra-high-rise tower with a height of 150 meters. After the completion of the project, it will further enhance the development level of the IC industry in Suzhou Hi-Tech Zone, adding impetus to the creation of the first district of national IC design as well as a national first-class green and low-carbon industrial highland.